Six-month delay for expansion of Taloja CETP
The proposed expansion of the MIDC common effluent treatment plant (CETP) at Taloja has been delayed by six months. The 5 MLD expansion work was to be completed by May 2020, but will now be completed in November. Shortage of technical staff, workers and delay in arrival of equipment has led to the delay.